Among the biggest projects is a $22.5bn plan to build a metro system in Riyadh.
Reuters/Riyadh/Khobar
Saudi Arabia is proceeding with public transport projects as scheduled and companies may face penalties if there are delays, Minister of Transport Abdullah al-Muqbil was quoted as saying by a leading local newspaper on Sunday.
With low oil prices slashing the government's export revenues and forcing it deep into deficit, the finance ministry has said it is trimming expenses, and there has been speculation that the budget for public transport infrastructure could be one victim.
Spanish train maker Talgo said in July that Saudi Arabia had cancelled a $201mn contract for six high-speed trains; neither the company nor the government gave a reason.
Some construction industry executives have reported delays in obtaining payment from Saudi government bodies, though others have experienced no problems and it is unclear if any delays are due to a tight budget.
Speaking to the al-Jazirah daily, Muqbil indicated there would be no major cutbacks to transport projects, which the government considers important to limit growth in domestic energy consumption and create jobs.
Public transport plan
He said the government had allocated 200bn riyals ($53.3bn) to be spent on public transport plans in cities with the highest population densities. He did not specify a time frame for that spending.
"Whether it is public transport projects or trains...the schedule of execution has been set by the Council of Ministers...Each project has a specific schedule and its execution is within an identified time frame with no delay," Muqbil said.
"Definitely, no delay is allowed on all the ministry's projects, whether roads or public transport...Violations will be spotted and penalties will be imposed on companies in charge of these projects."
Muqbil said bids were under evaluation to procure and operate buses for a 10-year public transport project in Makkah.
Among the biggest projects is a $22.5bn plan to build a metro system in Riyadh, to be completed in 2019; three foreign-led consortia were awarded contracts in July 2013.
Turki al-Sudairy, project coordinator at one of the Riyadh metro contractors, told Reuters that the project had experienced no delays at all and it was now about 21% completed, with completion still likely in 2019.
There are no comments.
Saying goodbye is never easy, especially when you are saying farewell to those that have left a positive impression. That was the case earlier this month when Canada hosted Mexico in a friendly at BC Place stadium in Vancouver.
Some 60mn primary-school-age children have no access to formal education
Lekhwiya’s El Arabi scores the equaliser after Tresor is sent off; Tabata, al-Harazi score for QSL champions
The Yemeni Minister of Tourism, Dr Mohamed Abdul Majid Qubati, yesterday expressed hope that the 48-hour ceasefire in Yemen declared by the Command of Coalition Forces on Saturday will be maintained in order to lift the siege imposed on Taz City and ease the entry of humanitarian aid to the besieged
Some 200 teachers from schools across the country attended Qatar Museum’s (QM) first ever Teachers Council at the Museum of Islamic Art (MIA) yesterday.
The Supreme Judiciary Council (SJC) of Qatar and the Indonesian Supreme Court (SCI) have signed a Memorandum of Understanding (MoU) on judicial co-operation, it was announced yesterday.
Sri Lanka is keen on importing liquefied natural gas (LNG) from Qatar as part of government policy to shift to clean energy, Minister of City Planning and Water Supply Rauff Hakeem has said.